How are government contracts paid? Net 30, WAWF and late payment
Federal agencies must pay 30 days after a proper invoice or acceptance, whichever is later. How WAWF and IPP work, and what to do when payment is late.
Federal contracts are paid by electronic funds transfer to the bank account in your SAM.gov registration, after you submit an invoice through the system named in your contract. Under the Prompt Payment clause (FAR 52.232-25), payment is due on the later of two dates: the 30th day after the billing office receives a proper invoice, or the 30th day after the government accepts the goods or services. If the agency pays after that date, it owes you interest without being asked. The rate for July 1 to December 31, 2026 is 4.75 percent.
Picture a small shop that delivers its first federal order, sends the invoice the same week, and plans its cash around being paid a month later. The month goes by. The invoice still shows as “under review.” Nobody has said anything is wrong, payroll is coming up, and the owner starts to think the government simply pays late.
Federal “net 30” carries two conditions. The invoice has to be proper, and the work has to be accepted. An invoice that sits “under review” past 30 days is often waiting on one of those two, and you can find out which.
How much do government contracts pay?
A federal contract pays the price written into it. There’s no standard government rate.
For scale, the Small Business Administration (SBA) scorecard for fiscal year 2025 shows $179.0 billion in prime contracts going to 56,725 small business contractors. Don’t read much into the average of those two numbers, because it would hide a very wide spread.
The SBA is direct about the upfront cost. Its guide says “Some businesses spend between $80,000 and $130,000 to earn their first contract”. So plan for the gap between doing the work and receiving the money.
When does the 30-day clock start?
The clause counts calendar days, and it treats payment as made on the date of the electronic funds transfer. The due date depends on the kind of payment.
| Payment type | Due date | Source |
|---|---|---|
| Most invoices | The later of the 30th day after a proper invoice is received and the 30th day after acceptance | FAR 52.232-25(a)(1) |
| Small business contractors | A goal of 15 days after receipt of a proper invoice and all other required documentation | FAR 32.009-1 |
| Construction progress payments | 14 days after the billing office receives a proper payment request | FAR 32.904(d) |
| Contracts with the Fast Payment Procedure clause | Within 15 days after the date of receipt of the invoice | FAR 52.232-25(c) |
Three details change the date in practice.
- For calculating interest, acceptance is treated as happening on the 7th day after delivery or performance, unless there’s a disagreement over quantity, quality or compliance.
- For work that isn’t a commercial product or service, the contracting officer may write a longer acceptance period into the contract.
- If the due date falls on a Saturday, Sunday or legal holiday, the agency may pay on the next working day without owing interest.
What is a proper invoice?
This is the first place the shop in the opening should look. FAR 52.232-25(a)(3) lists what a proper invoice must include:
- Name and address of the contractor.
- Invoice date and invoice number.
- Contract number, including order number and line item number.
- Description, quantity, unit of measure, unit price and extended price.
- Shipping and payment terms.
- Name and address of the contractor official to whom payment is to be sent.
- Contact details of the person to notify if the invoice is defective.
- Taxpayer Identification Number and banking information, where the contract requires them on the invoice.
- Any other documentation the contract requires, such as evidence of shipment.
If your invoice doesn’t comply, the billing office “will return it within 7 days after receipt”, with the reasons. You have to correct it and resubmit it before the 30 days can run.
Your bank details matter as much. Under FAR 52.232-33, the government pays using the banking information in SAM.gov. If that information is incorrect, the invoice is “deemed not to be a proper invoice” until it’s fixed. I’ve covered SAM.gov separately in the SAM.gov registration guide.
Do small businesses get paid faster?
Often, although the faster date is a goal. FAR 32.009-1 tells agencies to provide accelerated payments to small business contractors “with a goal of 15 days after receipt of a proper invoice and all other required documentation”. For civilian agencies this applies where the contract doesn’t set a specific payment date.
Don’t treat it as a second deadline you can enforce. The same section says the acceleration “does not provide any new rights under the Prompt Payment Act” and doesn’t change the late payment interest provisions.
What is WAWF, and what is IPP?
Your contract names the system you have to invoice through. These are the two you’re most likely to meet.
| System | Run by | What it does |
|---|---|---|
| Wide Area WorkFlow (WAWF), inside the Procurement Integrated Enterprise Environment (PIEE) | Department of Defense | Electronic invoicing, receipt and acceptance for defense contracts |
| Invoice Processing Platform (IPP) | Treasury, Bureau of the Fiscal Service | Invoicing from purchase order to payment notification for enrolled agencies. The IPP site shows more than 220 |
WAWF
The Department of Defense describes WAWF as “a secure Web-based system for electronic invoicing, receipt and acceptance.” It brings together the contract, the invoice and the receiving report.
DFARS 252.232-7003 requires defense contractors to submit payment requests and receiving reports through WAWF, with narrow exceptions. You can’t email the invoice instead: DFARS 232.7002 adds that “Facsimile, email, and scanned documents are not acceptable electronic forms”.
Under DFARS 252.232-7006 you need a designated electronic business point of contact in SAM.gov and a WAWF registration at wawf.eb.mil. The clause says contractors should use the web-based training and the practice site before submitting.
IPP
IPP is provided “at no charge to federal agencies and vendors”. You can submit invoices to enrolled agencies, check the status of an invoice or payment, and receive payment details.
What should you do when a payment is late?
Work through these in order. The first three tell you whether the clock ever started.
- Check the invoice status in WAWF or IPP. If it was returned, fix it and resubmit. If a proper invoice was rejected by mistake, FAR 32.906 says the original receipt date is used for the due date and for interest.
- Check acceptance. Ask the government acceptor or the contracting officer what is outstanding.
- Check your banking information in SAM.gov.
- Work out the due date. Then write to the payment office and the contracting officer with the contract number, invoice number, receipt date and acceptance date.
- Check that interest arrived with the payment. Under 5 CFR 1315.10 it runs from the day after the due date through the payment date.
- If interest of $1 or more isn’t paid within 10 days after the invoice is paid, send a written demand to the payment office, postmarked no later than 40 days after the invoice was paid. The clause then provides for an additional penalty.
- Ask the agency’s Office of Small and Disadvantaged Business Utilization for help. Under 15 U.S.C. 644(k)(6), its director “shall assist small business concerns to obtain payments, required late payment interest penalties, or information regarding payments due to such concerns from an executive agency or a contractor”.
- As a last step, submit a written claim to the contracting officer under the Disputes clause. FAR 33.206 allows 6 years from when the claim accrues. For a claim of $100,000 or less, FAR 33.211 lets you ask for a decision within 60 days.
Interest isn’t always owed. FAR 32.907 says the payment office won’t pay it when the delay is due to a disagreement over the payment amount or contract compliance, or for amounts withheld under the contract. It also says a temporary lack of funds “does not relieve an agency from the obligation to pay interest penalties.”
How are subcontractors paid?
If you’re a subcontractor, the prime pays you, under the subcontract. The 30-day rule covers what the government owes the prime. The FAR adds some protections for subcontractors.
| Rule | What it requires |
|---|---|
| FAR 52.232-40 | A prime that receives accelerated payments must pay its small business subcontractors within 15 days after receipt, “to the maximum extent practicable”, without charging a fee |
| FAR 52.232-27 (construction) | Each subcontract must oblige the prime to pay “not later than 7 days from receipt of payment” from the government, with interest if it pays late |
| FAR 52.242-5 | The prime must notify the contracting officer within 14 days when it pays a small business subcontractor a reduced amount, or more than 90 days past due, for work the government has paid for |
| FAR 42.1502(g) | Unjustified reduced or untimely payments are assessed in the prime’s past performance evaluation |
What a subcontractor can do
- Ask whether the prime has been paid. Under FAR 32.112-2 the contracting officer “shall promptly advise” a subcontractor whether the prime has submitted payment requests and whether final payment has been made. Contracts for commercial products or services are excluded.
- Report nonpayment. Under FAR 32.112-1, on contracts other than for commercial products and services, the contracting officer may check whether the prime has paid as the subcontract requires, and may encourage payment or, where the payment clauses allow, reduce or suspend progress payments to the prime.
- On a construction contract over $150,000, use the payment bond that FAR 28.102-1 requires. Under 40 U.S.C. 3133, a person not paid in full within 90 days after last supplying labor or material may bring a civil action on the bond, within one year.
- Speak to the contracting officer. A prime with a subcontracting plan has given an assurance that it won’t prohibit this (FAR 52.219-9).
Most of these leave the decision to the contracting officer. The government has no contract with a subcontractor, so the subcontract’s payment terms are your main protection. Read them before you sign. I’ve covered the rest of that relationship in the guide on becoming a government subcontractor.
FAR and DFARS text is from acquisition.gov as read on November 15, 2026, which showed Federal Acquisition Circular 2026-01, effective March 13, 2026. The FAR is being rewritten, so check the clauses in your own contract.
Sources
All sources were read on November 15, 2026.
- FAR 52.232-25, Prompt Payment (due dates, proper invoice, interest, additional penalty): https://www.acquisition.gov/far/52.232-25
- FAR 32.904, payment due dates (constructive acceptance, construction): https://www.acquisition.gov/far/32.904
- FAR 32.906, making payments (erroneously rejected invoices): https://www.acquisition.gov/far/32.906
- FAR 32.907, interest penalties: https://www.acquisition.gov/far/32.907
- FAR 32.009-1, accelerated payments (15-day goal): https://www.acquisition.gov/far/32.009-1
- FAR 52.232-33, payment by electronic funds transfer: https://www.acquisition.gov/far/52.232-33
- FAR 52.232-40, accelerated payments to small business subcontractors: https://www.acquisition.gov/far/52.232-40
- FAR 52.232-27, prompt payment for construction contracts: https://www.acquisition.gov/far/52.232-27
- FAR 52.242-5, payments to small business subcontractors: https://www.acquisition.gov/far/52.242-5
- FAR 42.1502, past performance policy: https://www.acquisition.gov/far/42.1502
- FAR 32.112-1 and 32.112-2, subcontractor nonpayment and requests for information: https://www.acquisition.gov/far/32.112-1 and https://www.acquisition.gov/far/32.112-2
- FAR 28.102-1, construction bonds: https://www.acquisition.gov/far/28.102-1
- FAR 52.219-9, Small Business Subcontracting Plan (assurance on discussing payment): https://www.acquisition.gov/far/52.219-9
- FAR 33.206 and 33.211, claims: https://www.acquisition.gov/far/33.206 and https://www.acquisition.gov/far/33.211
- DFARS 252.232-7003, electronic submission of payment requests: https://www.acquisition.gov/dfars/252.232-7003-electronic-submission-payment-requests-and-receiving-reports.
- DFARS 252.232-7006, WAWF payment instructions: https://www.acquisition.gov/dfars/252.232-7006-wide-area-workflow-payment-instructions.
- DFARS 232.7002, acceptable electronic forms: https://www.acquisition.gov/dfars/232.7002-policy.
- PIEE, WAWF Functional Information (description of WAWF): https://piee.eb.mil/xhtml/unauth/web/homepage/functionalInfo.xhtml
- Bureau of the Fiscal Service, Prompt Payment (interest rate): https://fiscal.treasury.gov/payments-from-government/prompt-payment
- Bureau of the Fiscal Service, Invoice Processing Platform (what vendors can do): https://fiscal.treasury.gov/payments-from-government/invoice-processing-platform-ipp
- IPP home page (no charge, number of agencies): https://www.ipp.gov/
- 5 CFR 1315.10, late payment interest, via Cornell Legal Information Institute: https://www.law.cornell.edu/cfr/text/5/1315.10
- 15 U.S.C. 644(k), agency small business offices, via Cornell Legal Information Institute: https://www.law.cornell.edu/uscode/text/15/644
- 40 U.S.C. 3133, payment bond actions, via Cornell Legal Information Institute: https://www.law.cornell.edu/uscode/text/40/3133
- SBA, basic requirements (first-contract cost): https://www.sba.gov/counseling/get-started/#basic-requirements
- SBA, Scorecard details, government-wide fiscal year 2025: https://www.sba.gov/certifications/scorecard-details/
Frequently asked questions
How are government contracts paid?
By electronic funds transfer to the bank account in your SAM.gov registration, after you submit a proper invoice through the system named in the contract and the government accepts the work. The standard due date is 30 days after the later of those two events.
What is WAWF?
Wide Area WorkFlow is the Department of Defense system for electronic invoicing, receipt and acceptance. It sits inside the Procurement Integrated Enterprise Environment (PIEE), and DFARS 252.232-7003 requires defense contractors to submit payment requests and receiving reports through it.
How much do government contracts pay?
A federal contract pays the price written into that contract. There is no standard rate. In fiscal year 2025 the SBA scorecard counted $179.0 billion in prime contracts to 56,725 small business contractors, which says nothing about what any single contract is worth.
Is net 30 guaranteed on a government contract?
The 30 days run from a proper invoice or from acceptance, whichever is later. If the invoice is returned as improper, or the agency disputes quantity, quality or compliance, the payment can take longer and no interest is owed for the period of the dispute.
Does the government pay interest on late invoices?
Yes. FAR 52.232-25 says the payment office will pay an interest penalty automatically, without a request from the contractor, when a proper invoice was received, the work was accepted without disagreement and payment was made after the due date.
How do subcontractors get paid on government contracts?
The prime contractor pays them under the terms of the subcontract. On a construction contract the prime must pay within 7 days of being paid by the government. A small business subcontractor can also tell the contracting officer that it has not been paid.