# Performance bond for a Singapore government contract: when is it needed and what does it cost?

> Singapore public construction contracts call the performance bond a security deposit. Your contract sets whether you need one and how much, and you can give cash or a guarantee.

- [Singapore](/sg/) /
- [Guides](/sg/blog/) /
- Performance bond for a Singapore government contract: when is it needed and what does it cost?

 Apply & bid

- Performance bond
- Singapore
- Security deposit

# Performance bond for a Singapore government contract: when is it needed and what does it cost?

Singapore public construction contracts call the performance bond a security deposit. Your contract sets whether you need one and how much, and you can give cash or a guarantee.

KSKetul Shah16 November 2026
· 9 min read
Copied

 The short version

In BCA's standard public sector construction contract (PSSCOC), the performance bond is called a Security Deposit. Clause 4.5 says you provide it within 14 days of the Letter of Acceptance, or a longer period set in the contract, for an amount stated in the contract's Appendix.

In this guide
- [What is a performance bond on a Singapore government contract?](#what-is-a-performance-bond-on-a-singapore-government-contract)
- [When is a security deposit needed?](#when-is-a-security-deposit-needed)
- [How much is the security deposit?](#how-much-is-the-security-deposit)
- [How do you provide it: cash, bank guarantee or insurance bond?](#how-do-you-provide-it-cash-bank-guarantee-or-insurance-bond)
- [What does a performance bond cost in Singapore?](#what-does-a-performance-bond-cost-in-singapore)
- [What can the agency do with the security deposit?](#what-can-the-agency-do-with-the-security-deposit)
- [When do you get it back?](#when-do-you-get-it-back)
- [Are there other guarantees?](#are-there-other-guarantees)
- [What to check before you bid](#what-to-check-before-you-bid)
- [Sources](#sources)
- [Frequently asked questions](#faq)

 Key takeaways
- In BCA's standard public sector construction contract (PSSCOC), the performance bond is called a Security Deposit. Clause 4.5 says you provide it within 14 days of the Letter of Acceptance, or a longer period set in the contract, for an amount stated in the contract's Appendix.
- You can pay it in cash or give a guarantee for the same amount from a participating financial institution under eGuarantee@Gov, or, with the employer's written consent, from a bank or MAS-approved insurance company.
- Tender Lite, for tenders with an estimated value not exceeding S$1 million, removes the security deposit, according to the Ministry of Finance. PSSCOC-lite leaves clause 4.5 blank.
- From 1 April 2025, guarantees for new government agency tenders that require them must be eGuarantees instead of paper.
- No official page we read gives a price for a performance bond. The amount comes from the contract, and any charge for a guarantee is set by the bank or insurer that issues it.

On Singapore public sector construction contracts, the performance bond is called a security deposit. BCA’s standard conditions say you provide it within 14 days of the Letter of Acceptance, unless the contract allows longer, for an amount stated in the contract’s Appendix. You can pay cash or give a guarantee for the same amount, and since 1 April 2025 such guarantees for new government agency tenders must be electronic. Tender Lite contracts, up to S$1 million, have no security deposit. No official page we read gives a price for a bond.

Picture a small builder that wins its first government contract worth a little over a million dollars. The Letter of Acceptance arrives with a two-week clock for the security deposit. The builder has priced the work, but not the cost of putting up security, and it does not know whether to hand over cash, ask its bank, or ask an insurer. It also wants to know when it will see that money again.

The answers are in the contract, and the standard clauses show you where to look before you price the job.

Everything below comes from BCA, Ministry of Finance, eGuarantee@Gov and GeBIZ pages we opened on 16 November 2026. We could not open Singapore Statutes Online that day, so we do not quote the Government Procurement Act or its Regulations.

## What is a performance bond on a Singapore government contract?

It is security for the work you have promised to do. The phrase most Singapore government documents use is “security deposit”.

BCA’s Public Sector Standard Conditions of Contract for Construction Works 2020 (PSSCOC, eighth edition), clause 4.5(1), says the contractor shall deposit with the employer “an amount specified in the Appendix and by way of security for the due performance of and observance by the Contractor of his obligations under the Contract”.

eGuarantee@Gov, the government platform for guarantees, describes a guarantee as “A banker’s guarantee or insurance bond”, issued by a financial institution. So whether someone says performance bond, banker’s guarantee, insurance bond or security deposit, you check the same things in the contract: what it requires, in what form and for how long.

## When is a security deposit needed?

The contract decides. Here is what the official documents we read say for each kind of contract.

ContractSecurity depositSource
Construction tender on the full PSSCOCYes, clause 4.5, amount in the AppendixBCA, PSSCOC for Construction Works 2020
Tender Lite, construction (PSSCOC-lite)No; clause 4.5 reads “Intentionally Left Blank”BCA, PSSCOC-lite for Construction Works 2025
Tender Lite, goods and servicesNo; MOF says Tender Lite removes the security deposit, and the Tender Lite conditions of contract we read have no security deposit clauseMOF procurement processes page; Tender Lite Conditions of Contract (goods and services)
Innovative Procurement Partnership pilotRemoved during the pilot phaseMOF procurement processes page
Full tender for goods and servicesSet by the tender’s own conditionsWe could not read a general rule

For full goods and services tenders above S$1 million, we did not find a published MOF rule saying when a security deposit is required or how much it is. Read the conditions of contract that come with each tender.

Tender Lite covers tenders with an estimated value not exceeding S$1 million. It began for general goods and services at the end of April 2024, for construction in May 2025 and for ICT in April 2026, according to MOF. Our guide to [quotations, Tender Lite and tenders](/sg/blog/quotation-vs-tender-lite-vs-tender-singapore/) explains the bands.

Coming to Singapore

Whether a contract needs a security deposit is in its tender documents, so it helps to see the right tenders early enough to read them and price it in. TrackTender sends a daily short list of tenders that match what you sell. TrackTender is not open in Singapore yet; it runs in India today.

 [Join the waiting list →](/sg/#waitlist)
 One email when it opens. No newsletter. No fee.

## How much is the security deposit?

The general conditions do not fix a percentage. Clause 4.5(1) of the PSSCOC refers to “an amount specified in the Appendix”, which is the contract-specific schedule the agency fills in for each tender.

So the figure is in the tender documents. When you read them, look for:

- the amount or percentage stated in the Appendix

- the period for providing it, if longer than 14 days

- the prescribed form of guarantee, also in the Appendix

Commercial websites quote percentages, but those are not government rules and we don’t repeat them here. Use the figure in the contract you are bidding for.

## How do you provide it: cash, bank guarantee or insurance bond?

Clause 4.5(2) of the PSSCOC, amended on 21 June 2024, lets you give a guarantee for an equivalent amount instead of cash. The guarantee can be issued by:

- a participating financial institution under the eGuarantee@Gov programme, meeting the requirements in the contract, or

- with the employer’s prior written consent, a bank or Monetary Authority of Singapore (MAS) approved insurance company, in the form set out in the Appendix.

### What is eGuarantee@Gov?

It is a government platform that digitises guarantees given to government agencies and schools. Its website says: “From 1 April 2025, it is mandatory for Applicants participating in new Government Agency tenders or applying for licences requiring guarantees to submit eGuarantees instead of paper guarantees.”

The steps on its site are short:

- Get the details you need from the agency (the beneficiary).

- Choose a participating financial institution from the list on the site.

- Give the institution the information; it issues the eGuarantee straight to the agency.

The site says no original hard copy guarantee is issued, and that issuance usually takes “less than 1 day (subject to other bank conditions such as credit limit)”.

## What does a performance bond cost in Singapore?

No official page we read gives a cost. The eGuarantee@Gov pages list no fee for a guarantee, and the BCA and MOF pages do not mention one.

Official pages do tell you what shapes the cost:

What decides itWhat the documents say
The amountSet in the contract’s Appendix under PSSCOC clause 4.5(1)
Cash or guaranteeCash is allowed; a guarantee is an alternative under clause 4.5(2)
Who issues the guaranteeAn eGuarantee@Gov participating institution, or with consent a bank or MAS-approved insurer
How long it stays in placeUntil the Final Completion Certificate, when the unused part is returned
The issuer’s own conditionseGuarantee@Gov notes issuance is subject to bank conditions such as credit limit

If you pay cash, the cost is the money tied up until it is returned, without interest. If you use a guarantee, ask your bank or insurer what it charges and what it needs from you, and compare that with the contract period. Any price a commercial provider gives you is its own offer, so we don’t quote such prices here as fact.

## What can the agency do with the security deposit?

Clause 4.5(3) says the employer may use the security deposit “to make good any loss or damage” from a breach of contract by the contractor, “including any liquidated damages”. If the guarantee is called, the cash proceeds become the security deposit.

If the employer uses more than the loss it actually suffered, it pays back the balance, without interest, to you or to the bank or insurer, when the Final Completion Certificate is issued. Clause 4.5(4) adds that the deposit does not limit the employer’s other rights to claim for breach.

## When do you get it back?

Clause 4.5(3) says that where the deposit was paid in cash, the employer pays back the unused amount without interest on the issue of the Final Completion Certificate.

Clause 34.1 says the Final Completion Certificate is issued within 30 days after the Defects Liability Period ends, or as soon after that as any work instructed under clause 18 (defects) is completed. So the security is held through the works and the defects period, and your guarantee or cash has to cover that whole span.

## Are there other guarantees?

Some contracts include an advance payment. Under Option Module D of the PSSCOC, for lump sum advance payments on prefabricated prefinished volumetric construction (PPVC), you must deliver an Advance Payment Guarantee “at his own cost” before or at the time the advance is paid, for the same amount as the advance. It can come from a bank or insurance company registered with MAS, a licensed finance company registered with MAS, or an eGuarantee@Gov participating institution.

Bidders sometimes ask about tender deposits too. We did not find a general rule on tender or bid deposits on the MOF and BCA pages we read, so check each tender’s instructions.

## What to check before you bid

- Is it Tender Lite? If so, the security deposit is removed.

- If it is a full tender, find the security deposit amount and period in the Appendix.

- Ask your bank or insurer now whether it is on eGuarantee@Gov and what it will need from you.

- Count the months from award to the end of the Defects Liability Period, plus up to 30 days.

If you are bidding on construction work, the workhead and grade still come first. Our guide to [BCA registration, workheads and grades](/sg/blog/what-is-bca-registration-workheads-grades/) covers those.

## Sources

All pages opened on 16 November 2026.

- Building and Construction Authority, Public Sector Standard Conditions of Contract for Construction Works 2020, eighth edition July 2020 (clause 4.5 Security Deposit, clause 34.1 Final Completion Certificate, Option Module D Advance Payment Guarantee): [https://isomer-user-content.by.gov.sg/338/5349d125-0337-4dc3-a36d-623e599f2865/1-psscoc-for-construction-works-2020.pdf](https://isomer-user-content.by.gov.sg/338/5349d125-0337-4dc3-a36d-623e599f2865/1-psscoc-for-construction-works-2020.pdf)

- BCA, Public Sector Standard Conditions of Contract Lite for Construction Works 2025 (clause 4.5 left blank): [https://isomer-user-content.by.gov.sg/338/1990d83f-085b-4aeb-9dfd-5cc086ae7273/6-1_psscoc-lite_constnwks.pdf](https://isomer-user-content.by.gov.sg/338/1990d83f-085b-4aeb-9dfd-5cc086ae7273/6-1_psscoc-lite_constnwks.pdf)

- BCA, Public Sector Standard Conditions of Contract (PSSCOC) page (list of PSSCOC and PSSCOC-lite documents): [https://www1.bca.gov.sg/growth-and-transformation/procurement/standard-contract-forms/public-sector-standard-conditions-of-contract-psscoc/](https://www1.bca.gov.sg/growth-and-transformation/procurement/standard-contract-forms/public-sector-standard-conditions-of-contract-psscoc/)

- Ministry of Finance, Procurement processes page, last updated 9 September 2026 (Tender Lite removes the security deposit; Innovative Procurement Partnership pilot removes security deposits; Tender Lite dates): [https://www.mof.gov.sg/policies/government-procurement/procurement-processes/](https://www.mof.gov.sg/policies/government-procurement/procurement-processes/)

- eGuarantee@Gov, Why eGuarantee@Gov page (definition of guarantee, mandatory eGuarantees from 1 April 2025, issuance time): [https://www.eguarantee.gov.sg/about-us/whyeguarantee/](https://www.eguarantee.gov.sg/about-us/whyeguarantee/)

- eGuarantee@Gov, Steps to apply page (three steps, no original hard copy issued): [https://www.eguarantee.gov.sg/steps-to-apply/](https://www.eguarantee.gov.sg/steps-to-apply/)

- eGuarantee@Gov, FAQ page (no fees stated): [https://www.eguarantee.gov.sg/faq/](https://www.eguarantee.gov.sg/faq/)

- GeBIZ, Conditions of Contract for Tender Lite (goods and services) (no security deposit clause): gebiz.gov.sg/docs/Tender_Lite_COCs_Supplier.pdf

## Frequently asked questions

How much is a performance bond for a Singapore government contract?

The amount is set in each contract. Under BCA's PSSCOC for Construction Works 2020, the contractor deposits 'an amount specified in the Appendix'. The general conditions do not fix a percentage, so read the Appendix and the tender documents for the figure.

What does a performance bond cost in Singapore?

No official page we read publishes a cost. If you give a guarantee instead of cash, it is issued by a bank or insurer, and the eGuarantee@Gov pages publish no fee for it. Ask the bank or insurer you use. The amount it guarantees and how long it must stay in place come from your contract.

Is a performance bond the same as a security deposit?

In Singapore public sector construction contracts, the standard conditions use the term Security Deposit for the security a contractor gives for the due performance of the contract. It can be cash, or a guarantee from a bank, an MAS-approved insurer or an eGuarantee@Gov participating institution.

Does Tender Lite need a security deposit?

No. The Ministry of Finance says Tender Lite removes the security deposit. In BCA's PSSCOC-lite for Construction Works 2025, the security deposit clause reads 'Intentionally Left Blank'.

When is the security deposit returned?

Under the PSSCOC, the unused part is paid back without interest when the Final Completion Certificate is issued. Clause 34.1 says that certificate is issued within 30 days after the Defects Liability Period ends, or as soon after that as any work instructed under clause 18 is completed.

Can I give a paper bank guarantee?

For new government agency tenders that require guarantees, eGuarantee@Gov says that from 1 April 2025 applicants must submit eGuarantees instead of paper guarantees.

KS

Written by Ketul Shah

Ketul Shah is the founder of TrackTender, a tender alert service that runs in India. These guides are researched from official Singapore sources, which are listed at the end of each one.

[More about TrackTender →](/about/)

Keep reading

## More guides

- [16 November 2026How do I check GeBIZ tender results and who won?GeBIZ publishes who won each quotation and tender and for how much. You can check results and the other bidders on GeBIZ, and look up past awards in MOF's data on data.gov.sg.](/sg/blog/how-to-check-gebiz-tender-results/)
- [16 November 2026How do I find Singapore government tenders, now that GeBIZ Alerts has ended?Singapore government quotations and tenders are published on GeBIZ. With the GoBusiness email alerts gone, here is how to search and get notified.](/sg/blog/how-to-find-singapore-government-tenders/)
- [16 November 2026How do I register as a GeBIZ Trading Partner, and is GeBIZ free?A GeBIZ Trading Partner account lets you bid for Singapore government work. Here is who can register, what you need first and what it costs.](/sg/blog/how-to-register-gebiz-trading-partner/)